“Bidirectional” has become a checkbox on EV spec sheets, and it hides three different things: a wall outlet in the trunk that runs a coffee maker at a campsite, a $5,000-to-$12,000 home installation that keeps the refrigerator and furnace on through a three-day outage, and selling power back to the grid, which almost nobody can do yet. Carmakers blur them, and a buyer who wants the second often ends up with the first. This page separates them, lists which US-market EVs offer each as of October 2026 with the hardware and output involved, and puts numbers on how long a car can run a house.
Three Features, Not One
- Vehicle-to-load (V2L) is AC power from the car itself: household outlets in the cabin, bed or trunk, or an adapter that plugs into the charge port. Typical output is 1.5 to 2.4 kW on crossovers and up to 9.6 or 10.2 kW on the pickups. It needs nothing installed. It cannot power a house through its wiring; you run extension cords to what matters.
- Vehicle-to-home (V2H) sends DC from the battery through a bidirectional charger and a transfer switch into the home’s panel, so the house runs normally with the grid disconnected. It needs specific hardware, an electrician, usually a permit, and a car whose software has been authorized for it. Output is set by the charger: 7 to 11.5 kW in current US systems.
- Vehicle-to-grid (V2G) exports to the utility for payment. In the US it exists as pilots: Nissan Leaf fleets through Fermata Energy, Tesla’s Powershare grid-support program for Cybertruck owners in parts of Texas, and school-bus projects. Private owners should not buy a car for it in 2026.
The practical test: if it works without an electrician, it is V2L. If the car can run the furnace, it is V2H, and the car is only half of what you are buying.
V2L: Which EVs Have Outlets
| Vehicle | Output | Where |
|---|---|---|
| Hyundai Ioniq 5, Ioniq 6, Ioniq 9 | About 1.9 kW in US spec | Adapter in the charge port; interior outlet on mid and upper trims |
| Kia EV6, EV9, Niro EV | About 1.9 kW | Charge-port adapter; interior outlet on most trims, two in the EV9 |
| Genesis GV60, Electrified GV70, Electrified G80 | About 1.9 kW | Charge-port adapter; interior outlet |
| Ford F-150 Lightning | 2.4 kW standard; 9.6 kW Pro Power Onboard option | Up to 11 outlets in frunk, cab and bed, including 240 V |
| Tesla Cybertruck | Up to 9.6 kW, Powershare | 120 V and 240 V outlets in the bed, 120 V in the cabin |
| Chevrolet Silverado EV, GMC Sierra EV | Up to 10.2 kW, PowerBase | Ten outlets including 240 V in the bed |
| GMC Hummer EV, Cadillac Escalade IQ | PowerBase outlets, lower totals | Bed and cargo area |
| Rivian R1T, R1S, R2 | About 1.5 kW per circuit | Bed, gear tunnel and cargo outlets |
| Lucid Gravity | About 1.8 kW | Cargo-area outlets |
| Nissan Leaf, 2026 | Adapter; about 1.5 kW | Charge port |
Notable absences: Tesla Model 3 and Model Y (apart from the Powershare change below), Ford Mustang Mach-E, Chevrolet Equinox EV and Blazer EV, Volkswagen ID.4, Honda Prologue, Toyota bZ, Nissan Ariya and the Mercedes and BMW lineups offer no outlets or adapter in the US. Several support V2H, which surprises people the other way: the Equinox EV can run a house with the right charger but not a toaster at a tailgate.
V2H: Who Can Power a House
The list below is manufacturer-confirmed systems you can buy and have installed in the US today, not announcements. Capability claims for the Hyundai Ioniq 5 and 6, Kia EV6, Rivian, Lucid and the new Leaf circulate widely; as of October 2026 none has a home-integration product on sale in the US, so they stay in the V2L table.
| Vehicle | Required hardware | Backup output | Status, October 2026 |
|---|---|---|---|
| Ford F-150 Lightning | Ford Charge Station Pro (80 A) plus Home Integration System, installed by Ford’s partner | 9.6 kW | On sale since 2022; the longest-running US system |
| GM Ultium: Silverado EV, Sierra EV, Hummer EV, Blazer EV, Equinox EV, Lyriq, Optiq, Vistiq, Escalade IQ and IQL, Celestiq, 2027 Bolt | GM Energy PowerShift Charger plus V2H Enablement Kit; optional PowerBank battery | Up to 10.2 kW on the trucks; crossovers lower | Available; some 2024 cars need a dealer or over-the-air update first |
| Tesla Cybertruck | Powershare Home Backup: Universal Wall Connector plus Gateway | 11.5 kW | Available |
| Tesla Model 3 and Model Y | Powershare, only on cars ordered from October 1, 2026, and only with a Powerwall 3 installed | Shared with the Powerwall | New; details still filling in |
| Kia EV9 | Wallbox Quasar 2 plus Kia Power Recovery Unit | About 11 kW | Available to eligible 2024–2025 owners by state, with waitlists; EV6 announced for late 2026 |
| Volvo EX90, Polestar 3 | Bidirectional hardware on board; home system through Volvo’s partners | Not yet published for US homes | Hardware-ready; confirm availability in your state before relying on it |
| Nissan Leaf, 2013–2025 | CHAdeMO bidirectional charger (Fermata Energy, dcbel) | Up to about 6 kW | Mostly fleet and pilot installations |
What a V2H Setup Costs
Ford’s Charge Station Pro lists around $1,300 and is included with extended-range Lightnings; the Home Integration System and installation through Ford’s partner typically bring the total to $5,000 to $10,000 depending on the panel. GM’s V2H bundle, the PowerShift charger and enablement kit, launched at about $7,300 before installation; the optional PowerBank battery adds more. Tesla’s Powershare hardware for the Cybertruck runs about $2,300 before installation, with installed quotes commonly $4,000 to $7,000. The Kia route, a Quasar 2 and Power Recovery Unit, has been quoted at $8,000 to $12,000 installed. Labor is the variable: a modern panel near the garage sits at the low end, a 100-amp panel that needs upgrading at the high end.
For scale, a Powerwall 3 installed runs about $15,000 and a standby generator $5,000 to $12,000 with gas plumbing. V2H lands between them and brings a bigger battery than any home unit: a Lightning carries nearly ten Powerwalls’ worth of energy. The federal charger credit that offset 30 percent of this equipment ended for installations after June 30, 2026; a handful of utilities, PG&E among them, run bidirectional pilots with incentives, and those are worth a call before signing.
How Long the Car Powers a Home
An average US home uses about 30 kWh a day; running essentials only, refrigerator, furnace fan, lights, internet, phones and a few outlets, it uses 8 to 15 kWh. Against usable battery:
| Vehicle, full charge | Whole house at 30 kWh/day | Essentials at 12 kWh/day |
|---|---|---|
| Chevrolet Silverado EV, 205 kWh | About 6 days | About 2 weeks; GM claims up to 21 days with rationing |
| Ford F-150 Lightning ER, 131 kWh | About 4 days; Ford says 3 typical | About 10 days |
| Tesla Cybertruck, 123 kWh | About 4 days | About 10 days |
| Kia EV9, 99.8 kWh | About 3 days | About 8 days |
| Chevrolet Equinox EV, 85 kWh | About 2.5 days | About 7 days |
Two deductions apply. Every system reserves a floor, usually 20 percent, so the car can still drive, which trims the figures above by a fifth. And in a winter storm the furnace runs more and the garage is cold, so plan on the essentials column, not the whole-house one. With V2L instead of V2H, the limit is the outlet rather than the battery: 1.9 kW runs a refrigerator, lights, a router and a space heater on low, not a well pump or an electric range.
Fine Print: Warranty, Range, Rules
- Battery warranty. Ford, GM, Tesla and Kia cover V2H use under the normal battery warranty with their own hardware. Third-party bidirectional chargers on unauthorized cars are where disputes start; the car’s software usually refuses the session anyway.
- Cycle count. A week of outage backup is a handful of full cycles on a pack rated for well over a thousand; daily V2G export would be a different matter, which is one reason it remains a pilot.
- Range after the storm. Set the reserve before you need it. The car will stop supplying power at the floor you chose and leave you with that much range, so on a crossover 20 percent is 50 to 60 miles.
- Permits and the transfer switch. V2H is a grid-isolation installation like a generator interlock; it needs a permit in most jurisdictions and must disconnect from the utility while supplying the house. Backfeeding a dryer outlet from a V2L cord is illegal and dangerous, and the car’s ground-fault protection will usually trip first.
- Charge port occupied. On E-GMP cars the external V2L adapter uses the charge port, so you cannot charge and supply power through it at once; the interior outlet works while charging.
- Cold. Output and efficiency fall when the pack is cold; a car kept in a garage supplies more usable energy than one in a driveway.
FAQ
What is the difference between V2L and V2H?
V2L is outlets on the car, 1.5 to 10 kW, with nothing to install; you run cords to appliances. V2H feeds the home’s electrical panel through a bidirectional charger and transfer switch, 7 to 11.5 kW, and requires $5,000 to $12,000 of hardware and installation plus a car authorized for it.
Which EVs can power a house in 2026?
With equipment you can buy today: the Ford F-150 Lightning, GM’s Ultium models including the Silverado EV, Sierra EV, Equinox EV and Blazer EV, the Tesla Cybertruck, Tesla Model 3 and Model Y ordered from October 2026 with a Powerwall 3, and the Kia EV9 for eligible owners. Hyundai Ioniq, Kia EV6, Rivian and Lucid offer V2L outlets but no US home system yet.
Can a Tesla Model Y power my house?
Only the newest ones. Tesla extended Powershare home backup to Model 3 and Model Y orders placed from October 1, 2026, and only alongside a Powerwall 3. Earlier Model 3 and Model Y cars have no bidirectional capability and no outlets.
Does using V2H hurt the battery?
Occasional outage backup adds a few full cycles a year to a pack designed for more than a thousand, and the manufacturers that sell V2H systems cover it under the standard battery warranty. Daily grid export would be different, and it is not offered to private owners yet.
Is V2L enough for a power outage?
For essentials, often yes: a 1.9 kW outlet keeps a refrigerator, lights, internet and phones running for days from an 84 kWh pack. It will not run central air, an electric range or a well pump; for those you need V2H or a generator.
Sources
- The Charge Port — V2H and V2G guide, October 2026: confirmed US V2H vehicles, hardware, Tesla Model 3/Y Powershare change
- Cali Energy — Confirmed US V2H vehicles, verified August 2026; Kia EV6 timing
- GreenLancer — V2L and V2H capability by model, October 2026
- Auto Edge View — Bidirectional charging guide 2026: outlet outputs, Quasar 2 compatibility
- Energy Scout — Ford Charge Station Pro and Intelligent Backup Power
- Home Power Vault — GM Energy PowerShift and PowerBank; Leaf CHAdeMO history
- Brainstamped — V2H equipment costs and backup-duration estimates
- Chariotz — V2H and V2L setup costs, 2026
- TaxGPT — Termination of the §30C charger credit for property placed in service after June 30, 2026